Security Clearance (Dec 2007) |
| |
|
CAIP employees certified to carry Government Full Security
Clearance for works on secure Government Establishments and
Government Projects. |
|
^ Back to Top |
 |
| |
|
Fibre Optics (Nov 2007) |
| |
|
CAIP awarded Enterprise project for fibre connections
between offices. |
| |
|
The works involved; feasibility study, design,
infrastructure installation and commission of a backbone
network connecting a cluster of offices for an expanding
medium sized enterprise. |
|
^ Back to Top |
 |
| |
|
Rig the Railway (Oct 2007) |
| |
|
Following the success of the earlier works on GSM-R, CAIP
have been awarded a further batch of rigging sites and tower
erection projects from a blue chip client. |
|
^ Back to Top |
 |
| |
|
Microwave Dish Decommission (Sept 2007) |
| |
|
CAIP have been awarded a large project to decommission a
redundant private microwave network. |
| |
|
The work is due for completion in June 2008 CAIP’s in-house
Transmission teams will carry out the work which also
involves Environmental Management under WEEE directives for
the safe disposal / resale of equipment. |
|
^ Back to Top |
 |
| |
|
On the Railways (Aug 2007) |
| |
|
CAIP have been awarded a series of sites on the GSM-R
project. |
| |
|
The works which involves tower erection, antenna install and
rigging must be carried out during the night and under tight
track possession windows. |
|
^ Back to Top |
 |
| |
|
Estates Works (Jul 2007) |
| |
|
CAIP has been awarded a series of estates projects from a
blue chip client. |
| |
|
The works involve a batch of sites where protracted legal
negotiations have lead to conflict and CAIP has been asked
to mediate, negotiate a closing settlement and remedy any
physical conditions outstanding. |
|
^ Back to Top |
 |
| |
|
Network Roll-out Isle of Man (Jun 2007) |
| |
|
CAIP are pleased to announce the successful completion of a
new 2g network on the Isle of Man. |
| |
|
The 35 sites were completed within a 3 month build window
just in time for the increased demand caused by the Isle of
Man TT motorcycle race. CAIP provided construction,
electrical, rigging, mechanical, logistics and optimisation
services on this incredibly "tight for time" project. |
| |
|
A huge thank you to all concerned on the successful delivery
of this very challenging project. |
|
^ Back to Top |
 |
| |
|
Client List Grows (Jun 2007) |
| |
|
Following the excellent UK wide delivery of construction and
M&E services, CAIP are pleased to announce the addition of a
further Blue Chip Company to our Client list. |
| |
|
Stand alone design, construction, mechanical, electrical and
data projects are underway and furthermore work has begun on
the development of plant asset registers to facilitate
planned, preventative and reactive hard maintenance
programmes starting in 2008 throughout the UK. |
| |
|
Ian Brooks (Director - Sales and Marketing) said, "the
introduction of this Blue Chip Client demonstrates that
clear parallels exist between the unique services offered by
CAIP within its traditional telecoms market and those
Clients who have reoccurring needs for bespoke UK wide
projects coupled with ongoing hard maintenance needs." |
| |
|
A huge thank you to all concerned with the development of
this work and its ongoing delivery. |
|
^ Back to Top |
 |
| |
|
Completion of New Offices - Elms Farm Barn (May 2007) |
| |
|
CAIP are proud to announce the completion of their new
offices in Warrington. |
| |
|
The dilapidated 4000 sg ft barn was acquired 18 months
previously and after a series of planning permission hurdles
construction work began 6 months ago. Using a combination of
specialist suppliers and CAIP's own internal trades
resource, the work has been undertaken under budget and on
time. |
| |
|
A huge thanks to all concerned and well deserved "topping
out party" is planned in the near future. |
|
^ Back to Top |
 |
| |
|
CAIP complete Isle of Man - Ronaldsway Indoor Solution (Apr
2007) |
| |
|
CAIP are pleased to announce the successful completion of
the Indoor coverage project undertaken within the Main
Terminal building at Ronaldsway Airport, Isle of Man. The
project for a Blue Chip Client was to improve 2g reception
to key areas within the terminal and CAIP's brief was to
supply: RF design, equipment design installation,
commission and integration services. |
| |
|
The project took 1 week to complete and has resulted in a
large uplift in available coverage both on the apron and
also within the terminal buildings. |
| |
|
Many thanks to the CAIP team in delivering this successful
project on time and on budget. |
|
^ Back to Top |
 |
| |
|
CAIP strengthens team (Mar 2007) |
| |
|
CAIP strengthen the team with the introduction of another
highly experienced Commissioning and Integrations Engineer. Working on CAIP's equipment recovery and swap out
programmes. Involved in projects with Nokia, Ericsson and
Nortel equipment should keep this latest member of the CAIP
team extremely busy. |
|
^ Back to Top |
 |
| |
|
CAIP appoint new Financial Director (Mar 2007) |
| |
|
CAIP are pleased to announce the appointment of Tony Allen
as Financial Director to the CAIP Group. Tony brings a
wealth of experience to the finance team and will only prove
to strengthen the CAIP top management tier. All at CAIP wish
Tony every success in rising to the challenges of working
within the fast moving telecoms sector. |
|
^ Back to Top |
 |
| |
|
Equipment Recovery (Feb 2007) |
| |
|
Utilising CAIP's in house resources a Blue Chip Client
requires the recovery of under-utilised, obsolete and end of
life equipment from its network. The programme involves all
of the multiple "on network" disciplines required to remove
equipment coupled with its safe handling from a variety of
difficult locations. |
|
^ Back to Top |
 |
| |
|
Equipment Swap works (Jan 2007) |
| |
|
Following on from the success of the first phase of this
highly skilled programme, CAIP is proud to announce its
involvement in the next 2 phases running from now until mid
year 2007. |
| |
|
As previously, those involved are expecting a challenging
programme with narrow outage windows with many "on network"
activities requiring close co-ordination. A big pat on the
back for those at CAIP's I&C teams for phase 1 and good luck
for phase 2. |
|
^ Back to Top |
 |
| |
|
Isle of Man (Jan 2007) |
| |
CAIP awarded contract for installing the Network for a
Global Blue Chip Client on the Isle of Man. Initial
pre-contract works began mid way through 2006 with January
2007 seeing the deployment of the first phase.
All those concerned are totally committed to delivery of the
project for commercial launch before the start of the
historic Isle of Man TT motorcycle races, which this year
celebrates its Centenary. |
|
^ Back to Top |